HomeMy WebLinkAbout06/15/1993, C-3 - WATERMAIN IMPROVEMENT PROJECT: BROAD - PEACH TO SERRANO, SPECIFICATION NO. 93-17. iIIIII�IY11l�llllln�lAl�lll 1" MEETING DATE:
cityo san Lals oBIspo ITS N�ems: 1993
COUNCIL AGENDA REPORT 3
FROM:
Mike McCluskey, Public Works Direct
Prepared by: Barbara Lynch, Engineering Assistant
SUBJECT:
Watermain Improvement Project: Broad - Peach to Serrano,
Specification No. 93-17 .
CAO RECOMMENDATION:
By Motion, Approve Plans and Specifications for Watermain
Improvement Project: Broad - Peach to Serrano, Specification No.
93-17, and Authorize Soliciting of Bids and Contract Award by CAO -if
the Lowest Responsible Bid is Within the Engineer's Estimate.
DISCUSSION:
The waterline in Broad Street is currently a six inch line. The line is
old and requires a great deal of maintenance. It is also undersized.
The project was included in a list of projects to be completed this year.
The Utilities Department has requested that this line be replaced. The
Fire Department has requested the addition of some hydrants.
CONCURRENCES:
The Planning Department has given this project a categorical exemption.
FISCAL IMPACT:
The engineer's estimate for the project is $270, 000. The Draft Capital
Improvement Plan for 1993/95 (page 5) includes $600, 000 for watermain
improvement projects for 1993/94 . Approximately $290, 000 has been
identified for other projects leaving $310, 000 to support this project.
The City Council at the June 30, 1992 meeting determined that Utility CIP
projects go forward based on their independent funding.
1992/93 CIP allocation remaining: $300, 000
1993/94 CIP allocation proposed: 600 , 000
Total to be budgeted: $900, 000
Less amount required for waterline
improvement project Spec. No. 93-15 (590, 000)
Total available: $310, 000
Plans and specifications are available in the Council Office for review.
�� atefYrpt\9317Wv