HomeMy WebLinkAbout03/00/1990, 4B - UTILITIES DEPARTMENT WORK PROGRAM MEETING DATE: l`I 1111 111 MY Of Sark z'..IIS OBISPO - March 5, 1990 9090 COUNCIL AGENDA REPORT Imo'NUMBER FROM: William T. Hetland, Utilities Director W Allen Short, Water Division Manger John Moss, Wastewater Division Manger SUBJECT: Utilities Department Work Program RECOMMENDATION: Review and provide appropriate direction with special emphasis on workload priorities. SUMMARY This report addresses the Utilities Department Work Program. A large portion of the document deals with the daily departmental functions and is familiar to the Council. It also summarizes the significant accomplishments that have occurred over the past year. The report discusses the Department's ability to accomplish administrative activities (those administrative functions separate from daily activities). The discussion reviews alternatives and concludes that clear priorities need to be established on the department's significant work activities. It also concludes that current staffing levels for administrative activities are adequate at this time providing no significant work projects are added. Operational staffing levels will be reviewed in future budget sessions. BACKGROUND This portion of the Mid Year Review Study Session deals with the Utilities Department Work Program. The report is divided into three sections. The first section addresses the department's normal day to day functions and specific goals and objectives. The second section outlines significant accomplishments that have occurred over the last year. The third section discusses the administrative activities of the department . It also presents options for accomplishing those tasks in the future. 1. Daily Activities The Utilities Department's primary function is to provide effective water and wastewater service to the City of San Luis Obispo. Over 90% of the staff and budget effort goes towards this goal. The Utilities Department has a staff of 45. Most of the staff operates water and wastewater treatment plants, maintains water distribution and sewage collection systems, and run water supply reservoirs and groundwater wells. Attachment #1 details the Utilities Department function. It is divided into the activity areas based on budget programs. Those areas are: WATER • Water Source of Supply • Power Generation • Water Treatment • Water Distribution • Water Customer Service • Water Conservation • Reservoir Operations • Whale Rock Fishing RECEIVED�e WASTEWATER R E C E I V E • Wastewater Pretreatment • Wastewater Collections • Wastewater Treatment MAIR 21990 /:ZS A At . CITY CLERK SAN LUIS OBISPO,CA /�y� ����n�i ►�NIIII � II city of san Lais oBispo COUNCIL AGENDA REPORT Utilities Department Work Program Page 2 ADMINISTRATION • Water Administration and Engineering • Wastewater Administration and Engineering Each section provides the basic program goal and a general description including the major activities of each program. Also included are the goals and objectives to be accomplished over the next budget cycle. Reportable budget objectives have been presented previously. Attachment #2 summarizes the status of the Utilities Department budget objectives. The staffing responsibilities section lists the approved budgeted positions. Each program description also includes a detail description of the personnel requirements for the current program listed as full time equivalent employees (FTE). Additional programs needs above what currently is being preformed and related personnel requirements, are tabulated. A large portion of this information is from the budget document which the Council has previously seen. The new information is primarily the additional program needs section for each program. Council may want to place their review emphasis on this area. The additional program needs portion identifies that the Water Section has a requirement of 1.0 additional FTE's and the wastewater section has a requirement of 6.1 FTEs. These additional program needs are summarized below: Water Treatment 1.0 Wastewater Pretreatment 0.6 Wastewater Collections 3.0 Wastewater Treatment 2.5 Total 7.1 The increase in employees results from the anticipated Inflow and Infiltration Program and the need for additional operators when the wastewater treatment plant expansion projects are working. In the short term, temporary contract employees will preform the required work tasks. The water distribution section is beginning to contract out a greater portion of the work (for example, Cla Val repair and raising gate wells) to meet the increased work load. Within the next year or two, staff will be able to recommend any necessary staffing changes for this area. Future annual budget sessions will include these additional employee requests when the timing is appropriate. 11. Sianificant Accomplishments Attachment #3 lists the significant accomplishments the Utilities Department has preformed over the last year. Some of the highlights include: • Department's reorganization efforts including the recruitment of key personnel • Continued telemetry system development • Pilot testing new treatment process alternatives at both the water and wastewater treatment plants • Implementation of a mandatory water conservation program • Development of groundwater wells and treatment systems �8 city of san .-ais osospo jIftZe COUNCIL AGENDA DEPORT Utilities Department Work Program Page 3 • Negotiation of a consent decree with the Regional Water Quality Control Board • Applied for a low interest loan for the wastewater management program • Made emergency repairs on the failed Laguna Lift Station 111. Administrative Activities The administrative activities of the department refer to functions other than basic daily operations. This primarily relates to coordination of large projects and being ready to respond to emergencies. These tasks are the most difficult and time consuming. In general, these would include special studies, planning, regulation compliance, requests for information, and organizational development. The administrative activities of the department and the individual time commitments are provided primarily by the following employees: Utilities Director .50 Water Division Manager .25 Wastewater Division Manager .25 Utilities Engineer (Vacant) .25 Administrative Analyst .50 Total 1.75 The time commitments should not be confused with the allocation of budgeted positions. The above estimates simply relate to the amount of time each individual spends on administrative activities separate from daily operations. This emphasizes one of the Utilities Department's key problems. There are less than two full time equivalent employees that are available to meet the Department's administrative demands. For an efficiently run department, it is necessary for the Director and Managers to spend time with the daily operations. The new reorganization moved some of the administrative responsibilities from the front line supervisors to the Managers when the Chief Operator and Crew Leader positions were eliminated. This places restrictions on the amount of time the Managers have for administrative activities. Attachment #4 lists the current responsibilities of the water and wastewater division managers. The following are alternatives for meeting the administrative needs of the Department. 1. Retain additional staff. 2. Delete work items. 3. Establish work item priorities and lengthen schedule for completion. 4. Use a combination of the above to maintain workload balance. The pros and cons of the above alternatives have been discussed often with the Council. Staff recommends that alternative #4, a combination of the alternatives, is most viable. To implement this requires that clear priorities be established. The Priority List is shown as attachment #5. The projects on the priority list have been ranked A - high priority, B - medium "11111111I11IN11U city of San Lacs OBISpo i111111194 COUNCIL AGENDA REPORT Utilities Department Work Program Page 4 priority and C - average priority. There are no low priority items because we do not have the resources available to perform low priority items. The Priority List is a dynamic process since the ranking is influenced strongly by deadlines we have no control over. Therefore when a deadline approaches the project develops a higher priority. Council is asked to review the ranking and suggest appropriate changes or Council priorities.. Staffs primary approach is to perform as much work in house as possible. There are situations wherein certain technical expertise is required. In those instances, it is more efficient to hire outside contractors or temporary staff. Though this saves staff time, it also requires administrative oversight on these contracts, which can be an equally significant commitment. Staff is recommending no additional personnel be retained at this time for handling administrative activities. The reorganization of the Utilities Department resulted in job responsibility changes and bringing a number of new people into unfamiliar positions. People are beginning to feel comfortable with their new responsibilities which should improve our work efficiency. In addition, the Department has added an Administrative Analyst to the staff. We are in the process of reviewing work assignments of the Director and Managers to determine which can be more appropriately handled by the Administrative Analyst. It will probably take another six months to sort all that out. The Utilities Department has also been without a Utilities Engineer since June of last year and has had difficulty in recruiting a replacement. Once that position is filled, it will also help the workload situation. Though a few of the Utilities projects are behind schedule, they are being completed. Our goal is to.continue to work on the high priority projects first then followed by projects whose priority changes due to approaching deadlines. The priority listing is based on the premise that no significant workload items will be added until others are either completed or reduced in priority. This does not take into account the recent Council action on desalinization and the per capita water conservation program. RECOMMENDATION Review and provide appropriate direction with special emphasis on workload priorities. Attachments I - 5 I 8' ATTACHMENT 1 PROGRAM: ADMINISTRATION/ENGINEERING OPERATION: WASTEWATER SERVICE DEPARTMENT: UTILITIES FUND: SEWER FUND PROGRAM DESCRIPTION The Wastewater Administration and Engineering Program directs and supervises the various wastewater programs and provides strategic planning and engineering. The program goals are the effective achievement of the wastewater program operating objectives and the implementation of capital improvement plans. MAJOR OBJECTIVES .1. Complete negotiations on the Consent Decree with the Regional Water Quality Control Board. 2. Obtain State loan- funding for implementation of the Wastewater Management Plan. STAFFING RESPONSIBILITY Director 0.4 Engineer 0.4 Administrative Analyst 0.5 Secretary 0..5 Total 1.8 Wastewater Division Page 1 i WASTEWATER ADMINISTRATION AND ENGINEERING ACTIVITY/PRIORITY PERSONNEL FTE'S . CURRENT PROGRAM Identify problems, establish objectives, organize resources and evaluate progress for wastewater utility management. 1.0 Determine capital improvement needs; develop preliminary designs and design standards for capital improvements. 0.3 Provide technical assistance to wastewater operating sections; review private development plans. 0. 1 Administer special engineering and construction. contracts. 0.4 CURRENT PROGRAM TOTAL 1.8 1989-90 PROGRAM RESOURCES 1.8 1990-91 PROGRAM RESOURCES 1.8 Wastewater Division Page 2 �t8- 7 PROGRAM: WASTEWATER PRETREATMENT OPERATION: WASTEWATER SERVICE DEPARTMENT: UTILITIES FUND: SEWER FUND PROGRAM DESCRIPTION The Wastewater Pretreatment program is a federally mandated program established to implement the objectives of the National Pretreatment Program. The program goal is to prevent the introduction of pollutants into the treatment system which: -Interfere with or inhibit the wastewater treatment process. -May pass through the system untreated or partially treated, causing a violation in state and federal requirements: -May contaminate the sludge, limiting its reuse or disposal. The pretreatment program consists of the legal authority, procedures, funding and personnel necessary to conduct the following five major activities: 1. Establish Nondomestic User Discharge Requirements - Develop legally defensible technical justifications for all discharge limits in the City's Sewer Use Ordinance; issue discharge limitation permits to each industrial user; enforce and update the City's Sewer Use Ordinance; research and recommend discharge requirements to the City as well as state and federal regulatory agencies. 2. Require Program Compliance - Identify all industrial users to be regulated under this program; require program compliance from all industrial users with federal and local discharge limits; require compliance schedules and programs from. violators; investigate and remedy instances of noncompliance; seek legal action for noncompliance. 3. Monitor Industrial Users - Perform permit compliance inspections on all industrial users on a regular basis; collect wastewater and process samples from dischargers and the collection system;. maintain sampling equipment. 4. Reporting and Record Keeping - Submit regular reports to state and federal regulatory agencies; undergo periodic program audits and inspections; maintain comprehensive computerized records on over 300 industrial users; develop and implement public relations activities. 5. Creek Discharge Activities - Investigate and take legal action against illegal discharges to stormdrains and surface waters in the City. Wastewater Division Page 3 7$ U PROGRAM: WASTEWATER PRETREATMENT OPERATION: WASTEWATER SERVICE DEPARTMENT: UTILITIES. FUND: SEWER. FUND MAJOR OBJECTIVES 1. Work with state and federal agencies as well as City's consultant to develop -a solution to the sludge/lead issue.. 2. Ensure final .adoption of the new Sewer Use Ordinance, establishing local discharge requirements and limitations. 3. Achieve full compliance with the requirements and recommendations of the Pretreatment_ Proaram _Comoliance Audit. STAFFING RESPONSIBILITY Industrial Waste Inspector 1. 0 Wastewater Division Manager 0.3 Total 1. 3 Wastewater Division Page 4 WASTEWATER PRETREATMENT PROGRAM ACTIVITY/PRIORITY PERSONNEL FTE'S CURRENT PROGRAM Reporting to City, County, State and Federal Agencies. Pretreatment program development. 0. 4 Administration and permitting of 300+ Industrial users._ 0. 3 Significant Industrial User monitoring, sampling and evaluation. 0.2 Compliance evaluation, correspondence and enforcement. 0. 15 Sewage spill investigation and reporting. 0. 05 Creek spill investigation and reporting. 0. 05 Collection system sampling for illegal discharges to the collection system. 0. 05 Lead/sludge contamination investigation through collection system sampling. 0.05 CURRENT PROGRAM TOTAL 1.25 ADDITIONAL PROGRAM NEEDS Increased inspection of industrial users other- than significant I/U's. 0. 4 Increased collection system sampling. 0. 1 Increased lead/sludge contamination investigation and increased collection system sampling. 0_1 ADDITIONAL PROGRAM NEEDS TOTAL 0.6 TOTAL PRETREATMENT PROGRAM 1.85 1989-90 PROGRAM RESOURCES 1. 5 FTE'S • 19.90-91 PROGRAM RESOURCES 1. 0 FTE'S CWastewater- Division Page 5 PAGE 11 - BLANK i PAGE 12 - BLANK O PROGRAM: WASTEWATER TREATMENT OPERATION: WASTEWATER SERVICE DEPARTMENT: UTILITIES FUND: SEWER FUND �Jl PROGRAM DESCRIPTION The wastewater treatment plant receives, treats and disposes of approximately 4. 5 million gallons of wastewater per day. The overall program goal is wastewater treatment that meets all standards set by state and federal agencies. Because -wastewater is discharged into San Luis Obispo Creek, state and federal agencies have imposed stringent discharge requirements. The City is also committed to increasing reclamation of the treated wastewater for reuse. The wastewater treatment program consists of five major activities: 1. Wastewater treatment operations - Receive, treat and. d,isinfect. wastewater; operate and calibrate treatment plant equipment systems; maintain, operate and evaluate treatment processes; operate and monitor a computerized treatment plant alarm, status and process control telemetry system; maintain records; prepare reports for local, state and federal agencies. 2. Laboratory analyses - Analyze untreated and treated wastewater; determine physical, chemical and biological characteristics of untreated and treated wastewater; evaluate treatment effectiveness; sample and test receiving waters for discharge parameters and impacts; develop and evaluate laboratory bench and pilot studies; prepare reports for local, state and federal agencies. 3 . Equipment maintenance - Perform routine inspection and preventive maintenance of treatment plant equipment; perform periodic repair of worn, inoperable or obsolete treatment plant equipment; maintain a computerized treatment plant equipment and system maintenance program. 4. Power generation - generate electricity for plant use from a 120 kilowatt methane gas operated powerplant; sell excess power to Pacific Gas and Electric. 5. Janitorial and curounds maintenance - Clean and tend; remove garbage and trash; perform minor building repairs; control weeds; repair irrigation systems; plant and replace low maintenance nursery stock; prevent soil erosion; repair fences; maintain plant pasture. Wastewater Division Page 6 y�8-13 J PROGRAM: WASTEWATER TREATMENT OPERATION: WASTEWATER SERVICE. DEPARTMENT: UTILITIES FUND: SEWER FUND MAJOR OBJECTIVES 1. Complete wastewater treatment pilot plant study in order to determine exact parameters for Full Compliance Option. 2 . Complete the following Capital Improvement Plan proects: -Treatment Plant Improvements, Units 3 & 4 . -Maintenance and overhaul of mayor plant equipment, clarifiers #1 & 3. Acquisition of two plant maintenance vehicles. -Phase 1 relief sewers/Infiltration and Inflow. STAFFING RESPONSIBILITY Wastewater Treatment Plant Supervisor 1. 0 Wastewater Treatment Plant Operators 6.0 Laboratory Technician 1. 0 Maintenance Worker 1. 0 Wastewater .Division Manager 0.4 Total Staffing 9.4 Wastewater Division Page 7 WASTEWATER TREATMENT PROGRAM ACTIVITY/PRIORITY PERSONNEL FTV S CURRENT PROGRAM Operations - Process control, evaluation and adjustment. 3. 0 Treatment process equipment repair and maintenance. 2 .25 Laboratory analyses. 1.25 Reporting and supervision. 0.5 Solids handling and mana-gement. 0.5 Janitorial, facilities and grounds maintenance. 1. 0 Power generation. 0_-5-5 CURRENT PROGRAM TOTAL 9.0 ADDITIONAL PROGRAM NEEDS Operations and maintenance of additional unit processes for full compliance (Units 3 and 4) . * 2_5 ADDITIONAL PROGRAM NEEDS TOTAL 2.5 TOTAL WASTEWATER TREATMENT PROGRAM 11.5 1989-90 PROGRAM RESOURCES 9 . 0 FTE'S 1990-91 PROGRAM RESOURCES 9. 0 FTE'S * Addition of 2 .5 FTE's for operation and maintenance of new unit processes is required prior to completion of units 3 and 4 construction, in 1992-93 FY. . OWastewater Division Page 8 yg -�s PROGRAM: WASTEWATER COLLECTIONS OPERATION: WASTEWATER SERVICE DEPARTMENT: UTILITIES FUND: SEWER FUND C PROGRAM DESCRIPTION The Wastewater Collection Program directs and oversees the transportation of wastewater from its various sources to the wastewater treatment plant via eight pump (lift) stations and approximately 150 miles of sewer mains. The program goal is to achieve uninterrupted sewage flout without health hazard, effluent leakage, or water infiltration and inflow (I/.I) . The program consists of three major service activities: 1.. Sewer main cleaning - Vacuum and/or flush all sewer mains as scheduled by a computerized preventive maintenance program; provide additional cleaning to problem mains; restore flow to blocked mains; repair broken mains; replace obsolete or damaged manhole equipment; inspect existing mains and those under construction for integrity; maintain computerized records of collection system maintenance; provide main location services. - 2 . Lift station operation and maintenance - Operate lift station pumping systems and telemetry system; using a computerized preventive maintenance program, maintain and repair lift station pumps and related systems; monitor lift station effectiveness and efficiency. 3 . Inflow and Infiltration evaluation - Monitor wastewater flows for I/I during wet weather; physically inspect and monitor collection system for indications of I/I during dry weather. MAJOR OBJECTIVES 1. Monitor .and analyze Tank Farm and Rockview lift stations flows to determine remaining capacity. 2. Complete the following Capital Improvement Plan projects: -Laguna Lift Station and Force Main Replacement. -Collection System Mainline Replacements. STAFFING RESPONSIBILITY Wastewater Collections Supervisor 1. 0 Utility Worker II 3 . 0 Utility Worker III 1.0 Wastewater Division Manager 0. 3 Total 5. 3 Wastewater Division Page 9 WASTEWATER COLLECTIONS PROGRAM ACTIVITY/PRIORITY. PERSONNEL FTE'S CURRENT PROGRAM Cleaning and maintenance of collection system lines. 3. 0 Investigation and repair of system failures. 0.5 Sewage lift station maintenance and repair. 0. 5 Safety. 0.25 System evaluation for CIP requirements." 0.25 Maintenance of sewer cleaning equipment. 0.25 Reporting and supervision. 0.25 CURRENT PROGRAM TOTAL 5.0 ADDITIONAL PROGRAM NEEDS Inflow/Infiltration investigation and repair.. 2 .0 Minor system repairs. (<$3, 000./repair) 1_0 ADDITIONAL PROGRAM NEEDS TOTAL 3.0 TOTAL WASTEWATER COLLECTIONS PROGRAM 8.0 1989-90 PROGRAM RESOURCES 5, 0 FTE'S 1990-91 PROGRAM RESOURCES 5.0 FTE'S Wastewater Division Page 10 _i PROGRAM: ADMINISTRATION/ENGINEERING OPERATION: WATER SERVICE �\ DEPARTMENT: UTILITIES FUND: WATER FUND �J PROGRAM DESCRIPTION The Water Administration. and Engineering Program directs and supervises the various water programs and provides strategic planning and engineering. The program goals are the effective achievement of the water program operating objectives and the implementation of capital improvement plans. MAJOR OBJECTIVES 1. Continue implementation of the Utilities Department reorganization. 2. Develop team building activities within the Utilities_ Department and strengthen relationships with other departments. STAFFING RESPONSIBILITY Director 0. 5 Engineer 0.5 Administrative.Analyst 0.5 Secretary 0.5 Total 2. 0 Water. Division Page 1 WATER ADMINISTRATION AND ENGINEERING ACTIVITY/PRIORITY PERSONNEL FTE'S CURRENT PROGRAM Identify problems, establish objectives, organize resources and evaluate progress for water utility 1. 0 management. Determine capital improvement needs; develop preliminary designs and design standards for capital 0.5 improvements. Provide technical assistance to water operating sections; review private development plans. 0. 1 Administer special engineering and construction contracts. 0.4 CURRENT PROGRAM TOTAL 2.0 1989-90 PROGRAM RESOURCES 2. 0 1990-91 PROGRAM RESOURCES 2. 0 Water Division Page 2 PROGRAM: SOURCE OF SUPPLY OPERATION:. WATER SERVICE DEPARTMENT: UTILITIES FUND: WATER FUND PROGRAM DESCRIPTION The Water Source of Supply Program provides for the procurement of raw water from its two sources: Whales Rock Reservoir and Salinas Reservoir. The program goal is to provide a clean, dependable supply of raw water for treatment at the water treatment plant. 1. Whale Rock Reservoir - The reservoir capacity is 40, 400 acre-feet and the City's entitlement is 55% of the safe annual yield of 4,800 acre-feet, or 2, 057 acre=feet. It is operated by the Whale Rock Commission by means of the Whale Rock Fund. Through the Source of Supply Program, the City pays the Whale Rock Fund its 55% share of the operational costs of the reservoir and the 100% cost of pumping raw water to its water treatment plant. 2. Salinas Reservoir - The reservoir has a 23, 000 acre-feet capacity and produces a safe annual yield of 4,800 acre-feet. Through the Source of Supply Program, the City provides for 100% of the costs of operating and transporting the raw water to its treatment plant. The reservoir is operated by the San Luis Obispo County Flood Control and Water Conservation District under contract to Army Corps of Engineers. MAJOR OBJECTIVES 1. Continue discussions to either obtain ownership of the reservoir or �. ' renegotiate agreement with the San Luis Obispo County Flood Control and Water Conservation District and the Army Corps of Engineers. 2. Complete Salinas Reservoir expansion feasibility study and begin final design. 3. Complete development of groundwater wells.. STAFFING RESPONSIBILITY None - Source of Supply is provided by other agencies. Water Division Page 3 ,yB �6 PROGRAM: POWER GENERATION OPERATION: WATER SERVICE DEPARTMENT: UTILITIES FUND: WATER FUND PROGRAM DESCRIPTION The Power Generation .Program has been established to reflect the costs of the City's hydroelectric power generation facilities. The program goal is to provide supplemental revenue for the water enterprise fund. The program is comprised of two major activities: 1. Stenner Canyon - In June 1985, the City completed construction of. a penstock and 750 kilowatt hydroelectric generator located near the retired water treatment facilities in Stenner Canyon. This plant harnesses the energy of water pumped from the Salinas Reservoir, which falls 700 feet through a delivery pipeline into the turbine and generator. The electricity generated is sold to Pacific Gas and Electric. 2. Plant Forebav - In December 1985, a private company under contract with the City completed construction of a 130 kilowatt hydroelectric generator at the water treatment plant forebay. Under this contract the company: receives a major portion of the hydroelectric revenues from Pacific Gas & Electric and pays the City a small percentage. of those revenues received. MAJOR OBJECTIVES 1. Modify Stenner Canon's radio recharging system to provide maximum recharging capability to reduce communication down time. 2. Install the utility-wide telemetry system at the hydro facility. 3. Remove the Stenner Canyon unit from service and conduct an extensive inspection and maintenance overhaul. 4 . Administer and monitor maintenance program for the Stenner .Canyon Hydro facility. STAFFING RESPONSIBILITY Provided by Water Treatment Plant Staff Water Division Page 4 IB -a� POWER GENERATION PROGRAM ACTIVITY/PRIORITY PERSONNEL FTE'S - CURRENT PROGRAM Monitor hydro performance., . collect and record . 10. operational data. Remove and return units to service as required. . 03 Trouble shoot units as. required. . 02 Administer maintenance contracts. . 01 Perform minor maintenance and clean up as required. . 03 CURRENT PROGRAM TOTAL .19 TOTAL PRETREATMENT PROGRAM . 19 1989-90 PROGRAM RESOURCES 0.0 1990-91 PROGRAM RESOURCES 0.0 Water_ Division Page 5 rTIf 'v� r I PROGRAM: WATER TREATMENT OPERATION: WATER SERVICE DEPARTMENT: UTILITIES FUND: WATER FUND PROGRAM DESCRIPTION The Water Treatment Plant receives approximately 3. 5 to 7 .5 million gallons of raw water each day depending on time of year and mandatory water conservation requirements. The raw water obtained is treated into potable water and delivered .into the City's water distribution system for storage, domestic consumption and fire fighting. The program goal is to provide an adequate water supply, which is treated to meet or exceed State and Federal water quality standards. MAJOR OBJECTIVES 1. Evaluate the effectiveness of potassium permanganate to mitigate taste an odor problems in the raw water. 2. Complete. the following Capital Improvement Plan pro ects: Ozone pilot study. Final phases of the Treatment Plant Upgrade Equip and make functional the new completed chlorine building. STAFFING RESPONSIBILITY Water Treatment_Plant Supervisor 1. 0 Laboratory Technician 1. 0 Water Treatment Plant Operator 5. 0 Instrumentation Technician 1. 0 Water Division Manager 0.3 Total 8. 3 Water Division Page 6 71 WATER TREATMENT PROGRAM ACTIVITY/PRIORITY PERSONNEL FTE-'S CURRENT PROGRAM Analyze raw, treated, and filtered water to determine constituent make up and to insure that the finished product meets or exceeds all State and Federal water quality requirements. 0.75 Monitor and evaluate process performance, trouble shoot and problem solve, and add chemicals and make adjustments as required. 2. 65 Perform equipment repair and required maintenance. 1. 65 Perform janitorial maintenance. .40 Prepare reports for Local, State, and Federal agencies. . 10 Administer and monitor laboratory quality assurance program: analyze well, raw .and treated water to determine physical, chemical and bacteriological characteristics and treatment effectiveness; collect and coordinate sample analysis; and calibrate all laboratory equipment. 1..0 Design, specify, install, program, troubleshoot and .60 maintain the Utilities telemetry system. Purchase, standardize and calibrate all required telemetry instrumentation. .40 Develop a weed control program. .03 Prepare a complete cost analysis and recommendation for pump replacement at the transfer pump house. . 06 Prepare a cost analysis and develop a replacement program for replacing plant fire extinguishers. . 07 Identify and label all electrical breakers. .07 Develop a liquid alum handling procedure. . 03 CURRENT PROGRAM TOTAL 8.30 Water Division Page 7 lie r� WATER TREATMENT PROGRAM ADDITIONAL PROGRAM NEEDS Receive and treat groundwater to State and Federal standards. .50 Add chlorine, and remove groundwater contaminants. .20 Prepare reports for Local, State and Federal .10 agencies. Perform maintenance and clean up as required. .20 ADDITIONAL PROGRAM NEEDS TOTAL 1. 00 TOTAL WATER TREATMENT PROGRAM 9.30 1989-90 PROGRAM RESOURCES 8.30 1990-91 PROGRAM RESOURCES 8.30 Water Division Page 8 PROGRAM: WATER DISTRIBUTION OPERATION: WATER SERVICE DEPARTMENT UTILITIES FUND: WATER FUND C� PROGRAM DESCRIPTION The Water Distribution Program provides for the delivery of potable water from the water treatment plant to water customers and fire hydrants via three storage reservoirs, six pump stations, six distribution reservoirs, and approximately 150 miles of water mains. The program goal is to provide uninterrupted water flow at adequate pressures with minimum water leakage. MAJOR OBJECTIVES 1. Develop and implement a Cla -Valve maintenance program; performing the necessary maintenance repairs on 10 of: the Valves. 2. Complete the distribution system Capital Improvement Program scheduled for 1989-90. Acquire vehicles for both telemetry and .water conservation. Telemetry system acquisition and installation. Evaluation and purchase of hardware and software for a computer based preventive maintenance. program. 3. Inspect and clean system storage tanks. 4. Implement a valve exercising program. STAFFING RESPONSIBILITY Water Distribution Supervisor .7 Heavy Equipment Operator 1. 0 Utility Worker 4 . 0 Water Division Manager 0.3 Total 6. 0 Water Division Page 9 yB-�Z 1 I WATER DISTRIBUTION PROGRAM. ACTIVITY/PRIORITY PERSONNEL FTE'S CURRENT PROGRAM Repair broken or leaking water mains and appurtenances; periodically inspect and clean all pressure reducing valves. 2.80 Inspect all pump stations weekly; lubricate and repair pumps and motors; paint pump houses and tanks; control weeds; tend landscaping, repair fences. .30 Install and connect new service lines, meters, and meter boxes. 1.70 Install and replace fire hydrants as needed. . 10 Prevent the backflow of harmful substances into the . io water system. Prevent galvanic and electrolytic corrosion of . 10 metallic lines and appurtenances. Valve exercising program. .40 Perform required documentation and supervision. . 30 Develop and maintain the City's Engineering Standards and Specifications line locate material which is to be included in each service and cul-de- sac installation. . 06 Establish a maintenance schedule and check list for the distribution system pumps and prepare it for entry into the maintenance software. . 05 Develop a map locating all valves in the downtown area to indicate those valves which are damaged or in need or repair. . 08 CURRENT PROGRAM TOTAL 6.29 TOTAL RATER DISTRIBUTION PROGRAM 6.29 1989-90 PROGRAM RESOURCES 6.0 1990-91 PROGRAM RESOURCES 6.0 Water Division Page 10 PROGRAM: WATER CONSERVATION OPERATION: WATER SERVICE DEPARTMENT: UTILITIES FUND: WATER FUND PROGRAM DESCRIPTION The Water Conservation Program provides for public education and information .regarding the wise use of water, relying on both voluntary and mandatory reductions in water consumption to meetprogram goals.. The program also includes a community retrofit program, water conservation ordinance development, enforcement and leak detection programs. MAJOR OBJECTIVES 1. 20 Percent overall mandatory reduction in water consumption. 2. Develop and implement a toilet rebate. program. 3. Develop and implement a water conservation marketing plan. STAFFING RESPONSIBILITY Water Conservation Coordinator 1.0 Water Division Manager 0.2 Total 1. 2 Water Division Page 11 WATER CONSERVATION ACTIVITY/PRIORITY PERSONNEL FTE'S CURRENT PROGRAM Provide the public with water conservation ideas, pamphlets, water use, and water saver guides. . 50 Provide for the entire City distribution system to be surveyed for leaks. . 10 Assist in ordinance enforcement; patrol the City during the summer months. .30 Develop and prepare water conservation policies for the reduction of water consumption. . 20 Provide public information concerning water development, treatment, and delivery including drip irrigation equipment, • drought tolerant plants, and retrofit devices. . 30 CURRENT PROGRAM TOTAL 1.40 TOTAL WATER CONSERVATION PROGRAM - 1989-90 PROGRAM RESOURCES 1.2 1990-91 PROGRAM RESOURCES 1. 2 Note: leak detection program is conducted by the water distribution system crew. Water Division Page 12 PROGRAM: WATER CUSTOMER SERVICE OPERATION: WATER SERVICE DEPARTMENT: UTILITIES FUNDI WATER FUND C PROGRAM DESCRIPTION The Water Customer Service Program measures water used by approximately 12,500 customers for billing and revenue purposes. . The program goal is to provide an accurate measurement of water usage as well as timely and regular billings. MAJOR OBJECTIVES 1. Implement the use of automated meter reading equipment (Utilicorders) into the daily activities of the meter reading program. 2. Develop and implement a preventive maintenance program for the sixty compound meter _ presently in the system. 3 . Retrofit 1,200 meters throughout the distribution system. STAFFING RESPONSIBILITY Water Distribution Supervisor 0. 3 Customer Service Representative 3.0 Water Division Manager 0. 1 Total 3 .4 Water Division Page 13 '��'20 WATER CUSTOMER SERVICE PROGRAM � ACTIVITY/P-RIORITY PERSONNEL FTE'S CURRENT PROGRAM Read approximately 6, 250 water meters per month; investigate abnormal readings; start/stop service; maintain access to and repair meters as required; respond to customer complaints. 1. 50 Replace obsolete meters over a seven year period, replace old/damaged meters on a 20 year schedule to conserve water and minimize billing errors. . 65 Remove large. commercial meters and contract for test and repair services on a four-year schedule. .25 Install new meters for new construction. .40 Prepare required documentation and supervision. .30 Investigate, review and select a computerized water . 05 meter maintenance program. Development- and implement the meter retrofit program, including development of a policy statement. .08 Develop specification, select and purchase a meter testing bench. .07 CURRENT PROGRAM TOTAL 3.40 1989-90 PROGRAM RESOURCES 3 . 4.0 1990-91 PROGRAM RESOURCES 3 .40 Water Division. Page 14 y�-�1 z PROGRAM: RESERVOIR OPERATIONS OPERATION: WHALE ROCK COMM. DEPARTMENT: UTILITIES FUND: WHALE ROCK FUND PROGRAM DESCRIPTION The Whale Rock Commission is a joint powers agency with six voting members who represent three state agencies and the City of San Luis Obispo. The Commission was formed to build the Whale Rock Reservoir and set policy for its operation. The City of San Luis Obispo, California Men's Colony (CMC) , and California Polytechnic. State University (Cal Poly) are the actual water users, sharing the costs and. benefits of the reservoir in proportion to their original investment: City (55%) ; Cal Poly (34%) ; and CMC (11%) . The Reservoir Operations Program provides for raw water storage in a 40,600 acre-foot reservoir and raw water delivery through 19 miles of. conduit and two pump stations to the agencies of the Whale Rock Commission. The program goal is to provide a reliable, easily treatable supply of raw water. MAJOR OBJECTIVES• 1. Installation of the Utility wide telemetry system at all Whale Rock Reservoir facilities. 2. Negotiate a formal lease agreement for percolation bonds below Whale Rock Dam. 3. Evaluate the feasibility of a. pump station. modification to improve the Whale Rock conveyance system during peak flow operations. STAFFING RESPONSIBILITY Water Supply Supervisor 1.0 Water Supply Operator 2 .0 Water Division Manager 0. 1 Utilities Engineer 0. 1 Utilities Director 0.1 Temporary as Full Time Equivalents 0.2 Total 3 .5 Water Division Page 15 "ICOtI �V RESERVOIR OPERATIONS PROGRAM ACTIVITY/PRIORITY PERSONNEL FTE'S CURRENT PROGRAM Collect, store, and pump raw water to member agencies and other customers., .65 Patrol, inspect and monitor the dam, reservoir, conduit and pump stations to prevent vandalism, contamination and insure safe operations. .80 Perform periodic preventive maintenance, repair damaged equipment, and replace worn and obsolete parts. .75 Prepare records and reports for Local, State and Federal agencies. .20 Prepare and monitor both line and CIP budgets. .05 Generate electricity from a 48 kilowatt turbine generator for sale to PG&E. .20 Monitor hydro performance, collect and record operational data. . 10 Remove and return units to service as required. . 03 Trouble shoot unit as required. . 02 Perform maintenance and clean up as required. . 03 Monitoring releases and pond water to recharge aquifers used for the town of Cayucos. .20 Supervision by Division Manager. . 10 Review and modify the current Whale Rock monthly summary sheet to correspond to the monthly report provided by Salinas reservoir. .20 CURRENT PROGRAM TOTAL 3.33 TOTAL WHALE ROCK COMMISSION PROGRAM 3.33 1989-90 PROGRAM RESOURCES 3 . 5 1990-91 PROGRAM RESOURCES 3 . 5 Water Division Page 16 PROGRAM: RESERVOIR OPERATIONS OPERATION: WHALE ROCK COMM. DEPARTMENT: UTILITIES FUND: WHALE ROCK FUND PROGRAM DESCRIPTION The Whale Rock Fishing Program provides for the operation and maintenance of the fishing facilities built in 1980-81. The program goal is to provide clean, functional fishing facilities without jeopardizing the purity of the raw water in the reservoir. The program also addresses requests from interest groups for improved access and an enhanced fishery. MAJOR OBJECTIVES• 1. Develop a list of facilities that raise rainbow trout to stock the reservoir. 2. Increase the native Dop_ulation of rainbow trout. Appropriate levels will be determined based on the number of fish caught vs the fees generated. . STAFFING RESPONSIBILITY . No Regular Positions Temporary Positions as Full time Equivalents 1. 1 Water Division Page 11 RESERVOIR OPERATIONS PROGRAM ACTIVITY/PRIORITY PERSONNEL FTE'S CURRENT PROGRAM - Collect fees; control admittance; provide direction .40 and advice. Patrol, and inspect the reservoir, to prevent vandalism, contamination and to insure safe fishing operations. .40 Perform periodic preventive maintenance, repair damaged equipment, and, replace worn and obsolete parts. . 10 Remove trash and litter and keep the fishing facilities clean. . 15 Collect a variety of information not limited to but including: number of fisherman, number of fish , caught and size. . 05 CURRENT PROGRAM TOTAL 1. 11 1989-90 PROGRAM RESOURCES (Temporary) 1. 1 1990-91 PROGRAM RESOURCES (Temporary) 1. 1 Water Division Page i8 r� ��� ATTACHMENT 2 C� O /8 y r,- UTILITIES DEPARTMENT �. BUDGET OBJECTIVES 1989 - 1991 PROGRAM DESCRIPTION % COMPLETED_BY BUDGET QUARTER 1989 1990 1990 1991 Dec. June Dec. June WATER SOURCE OF SUPPLY Continue discussions to either obtain 25 ownership of the reservoir or renegotiate. agreements with the Army Corps of Engineers and San Luis Obispo County Flood Control and Water Conservation District. (WTH) Complete Salinas River Reservoir expansion 75 feasibility study and begin final design.' (WTH) Complete development of groundwater wells (Capital Improvement Plan project). (AS) Phase I 100 Phase II 80 Phase ll1 0 POWER GENERATION Modify the radio recharging system to provide 30 maximum recharging capability to reduce communication down time. (AS) Install the Utility wide telemetry system at the 30 hydro facility. (AS) Remove unit from service and conduct an 0 extensive inspection and maintenance overhaul. (AS) WATER TREATMENT Evaluate the effectiveness of potassium 80 permanganate to mitigate taste and odor problems in the raw water (staff time only). (AS) Complete the following Capital Improvements Plan projects; (AS) Ozone pilot study 100 Final phases of Treatment Plant Upgrade Equipment for Chlorine Building 30 ' Reportable Program Objective 1 March 1, 1990 yrs-�� y_ UTILITIES DEPARTMENT BUDGET OBJECTIVES 1989 - 1991 PROGRAM DESCRIPTION % COMPLETED BY BUDGET QUARTER 1989 1990 1990 1991 Dec. June Dec. June WATER DISTRIBUTION Develop and implement a Cla valve 50 maintenance program and perform maintenance on 10 Cla valves. (AS) Complete the following Capital Improvement Plan projects: (AS) Acquisition of telemetry/conservation 50 vehicle Acquisition and installation of 20 telemetry system Distribution system improvements 5 Evaluation and purchase of hardware 50 and software for a computer based preventive maintenance program WATER CONSERVATION Achieve a 20%overall mandatory reduction in 100 water consumption. (AS) -Develop and implement a Toilet rebate 10 program. (AS) Develop and implement a water conservation 40 marketing plan. (AS) WATER CUSTOMER SERVICE Train in and implement the use of the 10 automated meter reading equipment (Utilicorders) into the daily activities of the meter reading program. (AS) Develop and implement a preventative 10 maintenance program for the sixty compound meters presently in the system. (AS) Retrofit 1,200 meters throughout the 5 distribution system. (AS) • Reportable Program Objective 2 March 1, 1990 7 cr -3g 1`1 UTILITIES DEPARTMENT BUDGET OBJECTIVES 1989 - 1991 PROGRAM DESCRIPTION % COMPLETED BY BUDGET QUARTER 1989 1990 1990 1991 Dec. June Dec. June ADMINISTRATION AND ENGINEERING Continue implementation of the Utilities 25 Department reorganization. (WTH) Develop team building activities within the 5 Utilities Department and strengthen relationships with other departments. (AI) WASTEWATER COLLECTION Monitor and analyze Tank Farm and 50 Rockview lift station flows to determine remaining capacity. (JM) Complete the following Capital Improvement Plan projects: Laguna Lift Station 50 Collection system replacements 10 C' WASTEWATER PRETREATMENT Work with state and federal agencies as well as 30 City's consultant to develop a solution to the sludge/lead issue. (JM)' Ensure adoption of the new Sewer Use 75 Ordinance, establishing local discharge requirements and limitations. (JM) Achieve full compliance with the requirements 75 and recommendations of the Pretreatment Program Compliance Audit. (JM) WASTEWATER TREATMENT Complete Wastewater Treatment Pilot Plant 100 study in order to determine exact parameters for Full Compliance Option. (JM)* " Reportable Program Objective 3 March 1, 1990 UTILITIES DEPARTMENT BUDGET OBJECTIVES 1989 - 1991 PROGRAM DESCRIPTION % COMPLETED BY BUDGET QUARTER 1989 1990 1990 1991 Dec. June bee. June WASTEWATER TREATMENT (continued) Complete the following Capital Improvement Plan projects: Treatment plant improvements 25 Relief sewers/infiltration and inflow 10 reduction Maintenance of major plant equipment 15 Acquisition of two (2) plant 80 maintenance vehicles ADMINISTRATION AND ENGINEERING Complete negotiations with the Regional Water 50 Quality Control Board on the City's consent decree. (WTH) Obtain State loan funding for implementation 25 of the Wastewater Management Plan. (WTH) \' RESERVOIR OPERATIONS Installation of the Utility wide telemetry 25 system at all Whale Rock facilities. (AS) Negotiate a formal lease agreement for 35 percolation ponds below Whale Rock Dam. (WTH) Evaluate the feasibility of a pump station 95 modification to improve the Whale Rock Conveyance system during peak now operations. (AS) WHALE ROCK FISHING Develop a list of facilities that raise rainbow 20 trout to stock the reservoir. (AS) Increase the native population of rainbow 10 trout. Appropriate level will be determined based on number of fish caught v, the fees generated. (AS) ' Reportable Program Objective 4 March 1, 1990 *7,& ATTACHMENT 3- LLD 1 _J WATER DIVISION SIGNIFICANT ACCOMPLISHMENTS 1989 Utilities Department Reorganization. - The development of the implementation plan. The revision of the work supervisors job descriptions. - Completed filling Key Supervisorial positions. Water Treatment Program - Completed system installation for the sewer collection section. Currently, 85 percent of the Water Treatment Plant, and Whale Rock system are installed. - Preparation and solicitation of an Request for Proposal (RFP) for and Ozone pilot study and treatment plant upgrade. - Completion of the potassium permanganate evaluation. This chemical allowed the treatment plant staff to continue to treat Salinas Water to its lowest historical level. - Both phase one and two are completed. - Purchase and installation of Carbon Filtration Units for contaminated wells. - Development and installation of a Zonal Booster pump Station. Water Conservation Program - Development and implementation of a 20 percent Mandatory Water Conservation Plan. - Hosting of the Water Awareness Fair. - Development and distribution of water conservation pamphlet "Every Drop Counts". Reservoir Operations - Preparation and solicitation of an Request for Proposal (RFP) Whale Rock Pumping and conveyance evaluation. - Completion of the Whale Rock pumping and conveyance system evaluation. - Development and construction of a well to a provide better management of the groundwater basin for the Cayucos Area Water Organization. - Salinas Dam Expansion study is approximately 80$ complete.. Water Distribution Program - Leak Detection Program identification and repair of and estimated 700 leaking water meters. C . l i Y WASTEWATER DIVISION SIGNIFICANT ACCOMPLISMIENTS 1989 1 Wastewater Pretreatment -Submission of Technical Justification For Local. Limits for EPA and State Review -Modify Sewer Use Ordinance to comply with EPA and State requirements and. provide legal authority for enforcement of pretreatment program regulations. -Industrial Waste Inspector- Recruited -Wastewater Division Manager Recruited -Pretreatment Program Compliance Audit -Phase 1 collection system monitoring for lead problem, 85% complete Wastewater Collection -Installation and. utilization of Hansen Computerized Maintenance Program =Laguna Lift Station Wet Well failureand emergency repair -Design of Phase 1 sewer main improvements project 85% complete -New Collection System supervisor on board -Installation of Computer Telemetry System for all lift stations including emergency condition alarms and standby notification Wastewater Treatment -Submittal of Loan Applications for SRF loans -Completion of Unit 3 design, Plans and Specs -Submittal of. Lead/Sludge Waste Classification to DHS -Submittal of sludge Storage Variance request to DHS -Completion of Wastewater Pilot Study -Completion of Value Engineering Study -Compliance with APCD regulations for sulfur discharges to the atmosphere -Initiate Project Report Preparation Draft completed -Draft EIR submittal for SRF Loan =Consent Decree development, 95% complete ��-1f3 ATTACHMENT 4 WASTEWATER DIVISION MANAGER TREATMENT: 1. Develop and adopt a revenue program and financing plan for wastewater facilities improvements, operations and maintenance. Adopt necessary sewer rate increases. Obtain State revolving fund loan. 2. Develop plans and specs for units 3 and 4 treatment plant improvements to achieve full compliance with state discharge requirements. 3. Approve construction management agreement for wastewater treatment plant units 3 and 4, and relief sewer construction projects. 4. Approve design contract for unit 4 improvements. 5. Develop and implement State revolving fund loans for wastewater reclamation. 6. Develop and implement a sludge management and disposal plan. 7. Develop Capital Improvement Plan projects to maintain and upgrade deteriorating and obsolete wastewater treatment plant equipment. 8. Monitor and control wastewater treatment plant operations and projects. PRETREATMENT ` 1. Develop sewer use ordinance revisions to enhance the effectiveness of the pretreatment program. 2 . Ensure technically justifiable local discharge limits for protection of the City's treatment system. 3. Develop and implement industrial users fees. 4. Continue to develop and modify the pretreatment program. 5. Monitor and control pretreatment program operations. 6. Ensure compliance with state and federal requirements for pretreatment programs. WASTEWATER DIVISION MANAGER COLLECTIONS 1. Develop, adopt and implement plans and specs for phase I relief sewer project. 2. Develop an- Inflow/Infiltration reduction program which includes the following: -ordinance changes to require lateral inspection and repair upon sale of property or building permits. -identification and correction of major inflow sources throughout the collection system including service laterals. -a financing system, e.g. assessment districts, to fund needed repairs. -engineering standards and testing procedures for all new collection system construction to protect against additional I/I. -identification and application of alternate pipe. repair/replacement processes to reduce the financial impact of I/I reduction. 3. Monitor and control collections system operations and maintenance ,programs. 4. Continue training and development of collections system personnel. 5. Develop Capital Improvement Plan projects for repair of deteriorated collection system main lines and equipment. 6. Evaluate remaining capacities of collection system ,main lines and lift stations. WATER DIVISION MANAGER CRESERVOIR OPERATIONS: 1. Assist in the development of an agreement for the Salinas Dam operation and licence. 2 . Develop a verification plan for Salinas Dam operations. 3. Coordinate Coastal Stream project both for the City of San Luis Obispo and the Whale Rock Commission. 4. Act as staff to Whale Rock Commission. 5. Complete Salinas Live Stream Analysis. 6. State Water Project. WATER TREATMENT• 1. Develop. the following Requests for Proposals: - Groundwater modeling - Desalinization - Cloud seeding - Land acquisition for movement of the Carbon Filtration tanks - Groundwater development phase 3. C2. Monitor and control treatment program operations. 3 . Ensure compliance with State and Federal requirements for treatment programs. WATER DISTRIBUTION: 1. Monitor and control telemetry system implementation. 2. Assist in the divisions classification study. WATER CONSERVATION: 1. Continue to develop and modify the water conservation program. 2 . Meet with a variety of groups and constituents regarding all aspects of water conservation. 3 . Develop and implement a toilet rebate program. CUSTOMER SERVICES: 1. Develop standards and ordinances for water meter installations. 2. Assist in the divisions classification study. —�i ATTACHMENT S �"LU UTILITIES DEPARTMENT WORK Loa® PfkroRrff UST C11' WATER WASTEWATER A. High Priority A. High Priority L. Groundwater Programs Request for 1. Complete Regional Board Consent Decree Proposals a. Groundwater basin yields 2. Continue with Wastewater Management b. Land acquisition for movement of Plan Implementation Carbon Filtration Tanks a. SRF Loan Program' c. Phase III well development b: Approve design contract for unit 4 c. Approve construction management 2. Water Conservation Program modification contract for units 3,4 and relief sewers and implementation d. Develop final revenue program e. Approve plans and specifications for 3. Complete Salinas Reservoir Expansion unit 3 and relief_ sewer construction study contracts 4. Organizational Development 3. Organizational Development B. Medium Priority B. Medium Priority 1. Coastal Streams Diversion Project 1. Develop and implement a sludge a. Complete EIR management program b. Determine institutional and financial a. Lead sludge issue arrangements b. Feasibility of composting 2. Salinas Live Stream analysis 2. Develop infiltration and inflow reduction program 3. Finalize Water Treatment Plant study and a. Lateral testing and repair upon sale of approve design contract property b. Identification of major system inflow sources c. Lateral replacement program d. Revise engineering standards e. Financing alternatives 3. Revise sewer use ordinance for pretreatment program to be in compliance with EPA requirements 4. Develop and implement industrial user fees I UTILITIES DEPARTMENT WORK LOAD PRIORITY LIST page 2 WATER WASTEWATER C. Average Priority C. Average Priority 1. Develop agreement for Salinas Dam 1. Develop technically justifiable local operation and license discharge limits for protection of treatment system 2. Develop Request for. Proposal for feasibility of Desalinization 2. Develop Wastewater Reclamation and Beneficial Reuse Program 3. Develop Request for Proposal for feasibility of Cloud Seeding I Develop long term Capital Improvement Program for relacement of deteriorating 4. State Water Project sewer lines a. Review of draft EIR b. Determination of Community Election 5. Annual Water Operational Plan Yearly Update 6. Review proposal for. San Luis Obispo Creek off-stream storage project 7. Maintain water action levels S. Select computer based maintenance program for water distribution i / 1 4B. UTILITIES DEPARTMENT WORKPROGRAM (HETLAND/202 - 60 min. ) (Report not received by agenda close-to be distributed under separate cover) . l