Loading...
HomeMy WebLinkAbout07-21-2015 C5 Bank Stabilization Project AwardCity of San Luis Obispo, Council Agenda Report, Meeting Date, Item Number FROM: Daryl R. Grigsby, Director of Public Works Prepared By: Dan Van Beveren, Senior Civil Engineer SUBJECT: TORO STREET BANK STABILIZATION, SPECIFICATION NO. 90646 PROJECT AWARD RECOMMENDATION 1. Award a contract to Souza Construction, Inc. in the amount of $111,088 for the construction of the Toro Street Bank Stabilization project, Specification No. 90646. 2. Approve the transfer of $48,197 from the Completed Projects account into the project’s construction account. DISCUSSION The Toro Street Bank Stabilization project consists of stabilizing two existing creek banks along San Luis Obispo Creek, and the removal of existing sediment which has accumulated beneath the Toro Street Bridge. Background San Luis Obispo Creek crosses under the Toro Street Bridge between Marsh Street and Pacific Street, and then continues in a northwesterly direction along the edge of Toro Street. The creek bank supporting Toro Street is very steep and consists of stacked sacks of concrete referred to as a “sack-crete” wall. The wall contains a void approximately five feet high and 70 feet long where the concrete sacks have been dislodged by the creek flow and washed away. The project will halt erosion under the wall. On the opposite side of the creek, a similar situation exists. A smaller sack-crete wall adjacent to the Toro Street Bridge and supporting the Dalidet Adobe property has also begun to erode. Both of these locations are in need of repair. The Toro Street Bridge is immediately upstream from these two creek bank locations. Over the years, sediment has accumulated on the north side of the bridge. The project includes removal of the sediment buildup to restore the creek flow capacity beneath the bridge. In 2014, staff completed the design for the Toro Street Bank Stabilization project. The project scope includes the restoration of the two damaged creek banks, and the removal of accumulated sediment beneath the Toro Street Bridge. A detailed discussion of the project scope is included in Attachment 1 - the City Manager Report authorizing the project advertisement. Due to the location of the project within the creek, regulatory permits were obtained from the Army Corps of Engineers, the California Department of Fish and Wildlife, and the California Regional Water Quality Control Board. One of the permit restrictions requires the project to be constructed between the dates of August 1st and October 31st – the time of the year when the creek flow is at its lowest. On July 21, 2015 C5 C5 - 1 Toro Street Bank Stabilization (90646) Page 2 March 10, 2015, the final permit was received, and the project was scheduled for construction later this year. City Manager Approval to Advertise The Engineer’s Estimate for the construction was $70,000, within the $100,000 limit of City Manager approval to advertise and award a construction contract. As such, the plans and specifications were approved by the City Manager on May 11, 2015. Bids were opened on June 11, 2015, and the lowest bid was $111,088, submitted by Souza Construction, Inc. The higher than expected bid amount is attributed by staff to the necessary dewatering of the creek, concrete forming and construction in a creek environment, and environmental permit compliance requirements, all of which are specialized types of construction activities difficult to estimate as they are not typical of most City projects. City Council Approval to Award Due to the bid amount being over $100,000, the City Council’s approval of the project award is required in accordance with the City’s purchasing policy. Staff has reviewed the bid by Souza Construction, Inc. for irregularities or special award circumstances and has found none. Therefore, staff recommends a construction contract to be awarded to Souza Construction, Inc. A copy of the Bid Summary is included as Attachment 2. FISCAL IMPACT The current project construction budget consists of $30,000 from $2012-13, and an additional $50,000 budgeted in the recently-approved $2015-16 CIP. With $128,196 needed for construction, a Budget Amendment Request will transfer $48,196 from the Completed Projects Account in order to supplement the current project budget as shown in the table below: Funding by Source Construction Costs Current Project Construction Budget:$80,000 Construction Contract:$111,088 * Completed Projects Account $48,196 Contingencies:$11,108 Total $128,196 Total for Construction $122,196 Materials Testing $5,000 Printing and other misc. costs:$1,000 Total for Other Costs $6,000 Total Construction Budget $128,196 Toro Street Bank Stabilization: Construction Budget and Funding * Current Amount Available in Completed Projects Account is $111,151. ALTERNATIVES Reject all bids and direct staff to re-advertise the project. The alternative to awarding the contract would be to reject all bids and to re-advertise. There are no indications that the construction costs would be any lower, and due to the seasonal restrictions of the project, the project would have to be rescheduled to 2016. This option is not recommended. C5 - 2 Toro Street Bank Stabilization (90646) Page 3 ATTACHMENTS 1. Copy of Original report authorizing advertising 2. Bid Summary 3. Contract Agreement with Souza Construction, Inc. AVAILABLE FOR REVIEW IN THE COUNCIL OFFICE Plans and Specifications t:\council agenda reports\2015\2015-07-21\toro street bank stabilization\90646 car-award.docx C5 - 3 THIS PAGE IS INTENTIONALLY LEFT BLANK C5 - 4 City of San Luis Obispo, City Manager Report Final City Manager Approval Approver Name Date Approved City Administration Michael Codron May 11, 2015 Reviewer Routing List Reviewer Name Date Reviewed City Engineer Barbara Lynch 4/20/15 City Attorney Jma 4/29/14 Finance & Information Technology mwP 5/1 April 17, 2015 FROM: Daryl Grigsby, Director of Public Works DRG 4/21/15 PREPARED BY: Dan Van Beveren, Senior Civil Engineer SUBJECT: Toro Street Bank Stabilization, Specification No. 90646 RECOMMENDATION 1. Approve Plans and Special Provisions for Toro Street Bank Stabilization, Specification No. 90646. 2. Authorize staff to advertise for bids. DISCUSSION The Toro Street Bank Stabilization project consists of the stabilization of two existing creek banks along San Luis Obispo Creek, and the removal of existing sediment which has accumulated beneath the Toro Street Bridge. Background San Luis Obispo Creek crosses under the Toro Street Bridge between Marsh Street and Pacific Street and then continues in a northwesterly direction along the edge of Toro Street. The creek bank supporting Toro Street is very steep and consists of stacked sacks of concrete referred to as a “sack-crete” wall. The wall contains a void approximately five feet high and 70 feet long where the concrete sacks have been dislodged by the creek flow and washed away. Continued erosion of this wall will increase the possibility of the collapse of the creek bank and the necessary closure of Toro Street. On the opposite side of the creek, a similar situation exists. A smaller sack-crete wall adjacent to the Toro Street Bridge and supporting the Dalidet Adobe property has also begun to erode. Both of these locations are in need of repair. The Toro Street Bridge is immediately upstream from these creek bank locations. Over the years, a minor accumulation of sediment has built up on the north side of the bridge. If left unmaintained, continued sediment accumulation could reduce the creek flow capacity beneath the bridge. Bank Restoration Staff from the Public Works Department has evaluated the deterioration of the existing sack-crete walls, and in conjunction with input from the City Biologist, has designed a repair which will stabilize ATTACHMENT #1 C5 - 5 Toro Street Bank Stabilization Page 2 the creek bank. The lower portion of the sack-crete wall, which has eroded away, is proposed to be stabilized with a new reinforced concrete retaining wall structure which will be built into and against the existing sack-crete wall. The new concrete wall would be more durable than the existing sack-crete wall and far more resistant to creek erosion. It would stabilize the wall in such a fashion that the existing creek bank could be salvaged with minimal disruption to the creek or the surrounding environment. The existing sack-crete wall above the concrete retaining wall structure would remain in place. Creek Diversion/Dewatering The proposed repair work is located within the flow area of the creek. In order to construct the retaining wall, the creek will need to be diverted around the work area. Creek diversion can be accomplished through the installation of an upstream dual check dam to hold back the water in the creek, and the temporary installation of two 12” bypass pipes which will carry the creek flow from the upstream location to a downstream discharge beyond the work area. Scheduling the work for the end of the dry season, when the creek flow is at its lowest, will facilitate the creek dewatering effort making it manageable to handle the minor creek flow typically occurring in the late summer and early fall. Boulder Clusters The project is located within the natural habitat of the steelhead trout – a species which is listed as threatened under the under the Endangered Species Act. Typical of any project within a sensitive environment, staff has considered the project’s impact on sensitive species and in this case, has included an enhancement within the project scope. Boulder clusters, which consist of a group of approximately eight boulders secured together and placed within the creek channel, will provide a potential habitat for the steelhead trout as well as other species within the project vicinity. The decision to include boulder clusters within the project is the result of staff consultation with regulatory agency staff which has provided input regarding the regulatory permitting for this project. Boulder clusters have been strategically designed along the outside of the creek channel with intent of diminishing the energy of the creek from the repaired sack-crete wall and redirecting the creek flow away from this outside bend in the channel. Sediment Removal The portion of San Luis Obispo Creek beneath the Toro Street Bridge is a location where the creek makes a gradual sweeping curve. Sediment has accumulated along the inside of this curve, resulting in several feet of material deposited along the northern portion of the creek beneath the bridge. The removal of this sediment is included in the project’s workscope to restore the flow carrying capacity beneath the bridge. The sediment material to be removed is primarily sand and gravel, and has been found to be useful as a fill material. After removing the sediment from the area beneath the bridge, the contractor will be permitted to use it as fill material elsewhere on the project. Regulatory Permitting This project is located within the creek, therefore, work must be scheduled for the late summer or early fall. That time frame is when water in the creek is lowest, and work can be performed with minimal impact to the flowing water within the creek. As such, scheduling this project around this limited construction timeline requires advance planning in both the design and regulatory permitting work. ATTACHMENT #1 C5 - 6 Toro Street Bank Stabilization Page 3 The project has received all necessary regulatory permits: A Section 404 Permit from the Army Corps of Engineers, A Streambed Alteration Agreement from the California Department of Fish and Wildlife, and a Section 401 Water Quality Certification from the California Regional Water Quality Control Board. Those permits contain specific requirements, all of which have been incorporated into the construction documents, or will be addressed through the efforts of City staff. CONCURRENCES The project’s design has been the result of team approach between the Public Works Department and the Natural Resources Division of the Administration Department. The City’s Community Development Department issued a Mitigated Negative Declaration for the project in August 2012. All mitigation measures identified in this environmental document have been incorporated into the project specifications. FISCAL IMPACT The 2015-17 Financial Plan proposes an additional $50,000 for the project’s construction budget. Because of the scheduling limitations noted above, this project is being recommended for advertising at this time, prior to the approval of the 2015-17 Financial Plan. If approved, this additional funding will be available on July 1, 2015, at which time staff will return to the City Manager for the project award. This financing contingency is disclosed to all prospective bidders on Page iii of the Notice to Bidders. The total construction budget is $80,000 which includes $30,000 of Measure Y funds budgeted in the 2011-13 Financial Plan, and a proposed additional appropriation of $50,000 from Measure G funds, pending the approval of the 2015-17 Financial Plan. ATTACHMENTS 1. Plans and Specifications \\chstore7\Team\City Manager Reports\Public Works\2015\CIP\90646 Toro Street Bank Stabilization\90646 eCM Advertise.docx Construction:70,000 Construction Contingencies:7,000 Total for Construction:77,000 Printing:1,000 Materials Testing:2,000 Total for other costs:3,000 Total Cost of Pro ject 80,000 ATTACHMENT #1 C5 - 7 THIS PAGE IS INTENTIONALLY LEFT BLANK C5 - 8 CI T Y O F S A N L U I S O B I S P O : B I D S U M M A R Y S H E E T Pr o j e c t : T o r o S t r e e t B a n k S t a b i l i z a t i o n S p e c . N o . : 90 6 4 6 Bi d O p e n i n g : 5- J u n - 1 4 Co n t a c t : Da n V a n B e v e r e n Es t i m a t e d f o l l o w u p d a t e s : Aw a r d : 7/ 2 1 / 2 0 1 5 Pr e - j o b : 8/ 6 / 2 0 1 5 En g i n e e r ' s E s t i m a t e S o u z a C o n s t r u c t i o n R . B u r k e C o r p o r a t i o n W h i t a k e r C o n s t r u c t i o n BI D I T E M & D E S C R I P T I O N UN I T T O T A L U N I T T O T A L U N I T T O T A L U N I T T O T A L No . I T E M U N I T Q U A N P R I C E P R I C E P R I C E P R I C E P R I C E P R I C E P R I C E P R I C E 1 Pe r m i t C o m p l i a n c e L S 1 1 5 0 0 . 0 0 $ 1 , 5 0 0 . 0 0 4 2 6 0 . 0 0 $ 4 , 2 6 0 . 0 0 1 5 2 0 5 . 0 0 $ 1 5 , 2 0 5 . 0 0 3 5 0 0 . 0 0 $ 3 , 5 0 0 . 0 0 2 Se d i m e n t R e m o v a l L S 1 7 5 0 0 . 0 0 $ 7 , 5 0 0 . 0 0 6 4 4 5 . 0 0 $ 6 , 4 4 5 . 0 0 1 3 7 0 0 . 0 0 $ 1 3 , 7 0 0 . 0 0 1 3 3 0 0 . 0 0 $ 1 3 , 3 0 0 . 0 0 3 Cr e e k D e w a t e r i n g L S 1 8 0 0 0 . 0 0 $ 8 , 0 0 0 . 0 0 1 2 1 0 9 . 0 0 $ 1 2 , 1 0 9 . 0 0 2 6 8 5 0 . 0 0 $ 2 6 , 8 5 0 . 0 0 4 1 0 0 0 . 0 0 $ 4 1 , 0 0 0 . 0 0 4 Re t a i n i n g W a l R e p a i r N o r t h e a s t S i d e o f C r e e k L F 65 5 0 0 . 0 0 $ 3 2 , 5 0 0 . 0 0 9 0 9 . 0 0 $ 5 9 , 0 8 5 . 0 0 8 7 0 . 0 0 $ 5 6 , 5 5 0 . 0 0 8 7 0 . 0 0 $ 5 6 , 5 5 0 . 0 0 5 Re t a i n i n g W a l R e p a i r S o u t h w e s t S i d e o f C r e e k L S 1 1 2 0 0 0 . 0 0 $ 1 2 , 0 0 0 . 0 0 2 1 5 3 9 . 0 0 $ 2 1 , 5 3 9 . 0 0 1 6 6 5 0 . 0 0 $ 1 6 , 6 5 0 . 0 0 2 3 2 5 0 . 0 0 $ 2 3 , 2 5 0 . 0 0 6 Bo u l d e r C l u s t e r s T O N 34 2 5 0 . 0 0 $ 8 , 5 0 0 . 0 0 2 2 5 . 0 0 $ 7 , 6 5 0 . 0 0 1 4 0 . 0 0 $ 4 , 7 6 0 . 0 0 3 5 0 . 0 0 $ 1 1 , 9 0 0 . 0 0 $7 0 , 0 0 0 . 0 0 $ 1 1 1 , 0 8 8 . 0 0 $ 1 3 3 , 7 1 5 . 0 0 $ 1 4 9 , 5 0 0 . 0 0 L i s t e d S u b s Central Valley Reiforcing Inc.Fresno, CA Co m m e n t s TO T A L no n e n o n e ATTACHMENT 2 C5 - 9 THIS PAGE IS INTENTIONALLY LEFT BLANK C5 - 10 AGREEMENT THIS AGREEMENT, made on this ______ day of ___________, 2015, by and between the City of San Luis Obispo, a municipal corporation and charter city, San Luis Obispo County, California (hereinafter called the Owner) and SOUZA ENGINEERING CONTRACTING INC., DBA SOUZA CONSTRUCTION INC., (hereinafter called the Contractor). WITNESSETH: That the Owner and the Contractor for the consideration stated herein agree as follows: ARTICLE 1, SCOPE OF WORK: The Contractor shall perform everything required to be performed, shall provide and furnish all of the labor, materials, necessary tools, expendable equipment, and all utility and transportation services required to complete all the work of construction of TORO STREET BANK STABILIZATION, SPECIFICATION NO. 90646 in strict compliance with the plans and specifications therefor, including any and all Addenda, adopted by the Owner, in strict compliance with the Contract Documents hereinafter enumerated. It is agreed that said labor, materials, tools, equipment, and services shall be furnished and said work performed and completed under the direction and supervision and subject to the approval of the Owner or its authorized representatives. ARTICLE II, CONTRACT PRICE: The Owner shall pay the Contractor as full consideration for the faithful performance of this Contract, subject to any additions or deductions as provided in the Contract Documents, the contract prices as follows: Item Item Unit of Estimated Item Price Total No. Description Measure Quantity (in figures) (in figures) 1 Permit Compliance LS 1 $4,260.00 $4,260.00 2 Sediment Removal LS 1 $6,445.00 $6,445.00 3 Creek Diversions & Dewatering LS 1 $12,109.00 $12,109.00 4 Concrete Creek Bank Protection #1 LF 65 $909.00 $59,085.00 5 Concrete Creek Bank Protection #2 LS 1 $21,539.00 $21,539.00 6 Boulder Clusters TON 34 $225.00 $7,650.00 BID TOTAL: $111,088.00 Payments are to be made to the Contractor in compliance with and subject to the provisions embodied in the documents made a part of this Contract. Should any dispute arise respecting the true value of any work omitted, or of any extra work which the Contractor may be required to do, or respecting the size of any payment to the Contractor, during the performance of this Contract, said dispute shall be decided by the Owner and its decision shall be final, and conclusive. ARTICLE III, COMPONENT PARTS OF THIS CONTRACT: The Contract consists of the following documents, all of which are as fully a part thereof as if herein set out in full, and if not attached, as if hereto attached: 1. Notice to Bidders and information for bidders. ATTACHMENT #3 C5 - 11 2. Standard Specifications, Engineering Standards, Special Provisions, and any Addenda. 3. Accepted Bid. 4. Public Contract code Section 10285.1 Statement and 10162 Questionnaire. 5. Noncollusion Declaration. 6. Plans. 7. List of Subcontractors. 8. Agreement and Bonds. 9. Insurance Requirements and Forms. ARTICLE IV. It is further expressly agreed by and between the parties hereto that should there be any conflict between the terms of this instrument and the bid of said Contractor, then this instrument shall control and nothing herein shall be considered as an acceptance of the said terms of said bid conflicting herewith. IN WITNESS WHEREOF, the parties to these presents have hereunto set their hands this year and date first above written. ATTEST: CITY OF SAN LUIS OBISPO A Municipal Corporation __________________________ By: _________________________ Anthony J. Mejia Jan Howell Marx City Clerk City Mayor APPROVED AS TO FORM: CONTRACTOR: Souza Engineering Contracting Inc., DBA Souza Construction Inc. By: __________________________ J. Christine Dietrick Steve A. Souza City Attorney Its: President Rev. 12-28-09 ATTACHMENT #3 C5 - 12