RESIDENT ENGINEER'S DAILY INSPECTION REPORT
Men
LOCATION AND DESCRIPTION OF OPERATION:
Start
Stop
Diary:
Signature:
Title: Engineer Inspector
Materials:
Weather: Dry/Clear </
Date
Curley Labor
James Y Foremen
James D Labor
Jano Y Labor
Manuel B Labor
JD -50 MINI EX
350SG BACKHOE
BOBTAIL
CREW TRUCKS
CONCRETE SAW
Specification 91436
D-Kal Engineering
Bobtail
rental
Jose Labor
Mike Labor
Jake Labor
Ted Operator
tiein
Chorro street tie in
9:00 AM: Contractor is tying over one services and changing out meters on Chorro.
Also strated potholing street for tie-in starting at 2pm to 6pm.
2pm Jerry and Ryan are on site water is shut down.
D-Kal has 2 crews working on site one at Pismo and one at Pacific.
4pm while excavating to remove thrust from existing watermain contractor found a abandoned 8'' waterline and valve. Contractor was missing some correct fitting for tie-in and was delayed
because they had to go pick up correct fittings. exsample was megalug fittings for DI rather than PVC. MJ glands rather than meg a lugs.
After removing the existing abandoned main found existing SD slope 15% and was in conflict with tie -in.
4:30 pm I directed contractor to install new line under existing SD.
8:00 pm water back on at Pismo.
9:30 pm water back on at Pacific fire alarm whent off at 881 Pacific FD on site I called disspatch to inform them.